
|
|
||
|
|
|
Minnesota State
INTERSTATE 35
Minnesota State
State Hwy 10

In August 2006 Gladen Construction Inc. started construction with
Hardrives Inc. on a 11 million dollar interstate 35 project between Hinckley
and Rock Creek MN. The work involved constructing cross over bypasses to
facilitate temporary two way traffic. Once two way traffic was moved onto
the temporary bypass Gladen Construction Inc. was given twelve working days
to complete the south bound phase of the project. This work consisted of
culvert rehabilitation and frost heave corrections. The work was completed
ahead of schedule and four lanes of traffic was restored one weekend early.
The culvert rehab and frost heave work was completed on the northbound lanes
on September 22, 2006. This was the first mainline interstate project for
our company. The only work for Gladen Construction Inc. in 2007 will be some
minor extra work on the northbound lanes.

First Vehicles On The New Section of Interstate 35

North Dakota State
State Hwy 81
Removing Common
Excavation
Hwy. #81.
Placing of the grouted and hand brushed into place to make grouted rip rap.
Installing Quad
reinforced centerline pipe acrossed
Hwy #81.
Gladen Construction Inc. was the prime contractor
worked on State Highway #81 that started from west highway #66 and north 14
miles to Highway #5 at Hamilton. This included over 470,746 cubic yards of material from topsoil,
and common excavation. Also on the project we hauled and placed
over 107,886 tons of class 5 and class 3. This project also had 13,982 feet of reinforced concrete and corrugated
metal pipe.
Inspector John explaining to the crew how he would like to see them Git'r Done.
North Dakota State
State Hwy #2

Gladen Construction Inc. constructed one and a half miles of railroad grade along with some structure connections. We also installed approximately one thousand liner feet of sanitary sewer along with a lift station thirty five feet deep, three five hundred liner feet of storm sewer, and thirteen hundred liner feet of water main.


Below are pictures of our equipment that was hauled by railroad flat cars to the North Dakota State Hwy #2 project.

State Hwy 71



Gladen Construction Inc. a subcontractor for North Star was involved during July 18, 2005 - August 12, 2005 in working on nine miles of State Hwy 71 south of Bemidji Minnesota. Approximate 1,390 feet of pipe was removed and then replaced with about 1,500 feet of pipe. Some of the pipe was bored under the road so that no construction would need to take place to the road top. Gladen Construction Inc. was also responsible for moving and placing 35,750 cubic yards of dirt to create new right turn lanes as well as bypass lanes along the nine mile stretch of road.
